Jul 10, 2012
Quad Construction Update July 10, 2012
Fencing – We do not anticipate any major changes until Step 3. Traffic – The Clinton Terrace crosswalks will be finished by the end of the day tomorrow…
Fencing – We do not anticipate any major changes until Step 3. Traffic – The Clinton Terrace crosswalks will be finished by the end of the day tomorrow…
Fencing – We do not anticipate any changes to the layout until Step 3. Traffic (Clinton Terrace) – Crews started to construct…
Fencing – Whiting-Turner does not anticipate any changes to the layout until Step 3. Traffic – Starting the end of this week and…
Fencing – The construction crews have expanded the south construction site to include the areas in front of Farinon Center and Hogg Hall. Farinon’s…
Fencing – The construction team is planning two layout changes: The first will take place around noon June 14 and will include expansion of the south…
UGI informed Whiting-Turner this morning that it is halfway through the design for the gas line relocation in front of Farinon. UGI is planning on mobilizing…
Fencing – The construction team is anticipating two changes to the fence layout. The first will take place either late this week or early next week and…
Fencing – Fencing for Step 1, Part 1 has been completed. Fencing for Step 1, Part 2 will take place around the middle of June, when it will be extended…
Fencing – Fencing for Step 1 started May 22 and will be completed May 23. A reminder: The High Street parking lot is now closed off. Clinton Terrace…
This is a reminder that parking will no longer be available on Quad Drive and East Campus Lane effective Monday, May 21, as Phase II of the transformation…