Sep 13, 2012
Campus-Wide Email Sept. 13, 2012
To: Lafayette Campus Community From: Offices of Public Safety and Facilities Planning & Construction Re: Update on the Temporary Traffic Adjustments for…
To: Lafayette Campus Community From: Offices of Public Safety and Facilities Planning & Construction Re: Update on the Temporary Traffic Adjustments for…
Construction – Crews are pouring concrete slabs for the southern paths between the Farinon Center and Skillman Library, which will allow the hardscape…
Progress – Crews are working on the southern paths for the project between Farinon and Skillman Library. A separate crew is setting the granite pavers…
Skillman Library – There are two access paths leading to the front entrance of Skillman. Clinton Terrace – Clinton Terrace is only open for deliveries…
Fencing – The fencing along High Street in front of Markle Hall will be removed today to allow vehicles and pedestrians to use the roadway and sidewalks…
Fencing – This week, additional fencing will be installed around High Street in front of Markle Hall to establish a construction perimeter around the…
Fencing – The project is in a transition phase from Step 2 to Step 3 until this afternoon. Fencing will be removed in front of Hogg Hall, the Farinon…
Fencing – Two layout changes will be made Tuesday or Wednesday next week. Select fencing between Markle Hall and Skillman Library will be removed…
Fencing – High and Sullivan were fenced off Monday to allow construction crews to start reconstructing that intersection. Later this week, additional…
Fencing – We anticipate two changes to the layout next week. The first will be additional fencing at the intersection of High Street and Sullivan Road…