Quad Construction Update July 10, 2012
Fencing – We do not anticipate any major changes until Step 3. Traffic – The Clinton Terrace crosswalks will be finished by the end of the day tomorrow…
Fencing – We do not anticipate any major changes until Step 3. Traffic – The Clinton Terrace crosswalks will be finished by the end of the day tomorrow…
Fencing – We do not anticipate any changes to the layout until Step 3. Traffic (Clinton Terrace) – Crews started to construct…
Fencing – Whiting-Turner does not anticipate any changes to the layout until Step 3. Traffic – Starting the end of this week and…
Fencing – The construction crews have expanded the south construction site to include the areas in front of Farinon Center and Hogg Hall. Farinon’s…
Fencing – Fencing for Step 1, Part 1 has been completed. Fencing for Step 1, Part 2 will take place around the middle of June, when it will be extended…
In accordance with the campus wide parking and transportation study, the College has recently created significant additional parking on and around campus…
This project includes renovation of the gardens, using the historic design concepts from 1914, benefiting the McKelvy Scholar experience.[nggallery id=23]…
This new campus, made possible largely by generous support from longstanding College donors and the Commonwealth of Pennsylvania’s Redevelopment Capital…
Estimated construction start date May 2012 To view the complete presentation about the project logistics including phasing of this project, please click…
Construction underway Estimated completion date early May 2012