Dec 18, 2012
Quad Construction Update Dec. 18, 2012
Construction: The grounds improvement project is wrapping up for the season. The fencing has been removed and the landscape crew is working on the last…
Construction: The grounds improvement project is wrapping up for the season. The fencing has been removed and the landscape crew is working on the last…
Construction – After the northern path is done early next week, irrigation and landscaping work will continue up to it. Please be cautious of the large…
Construction – New brick pavers and bluestone are being installed along the northern path. Later this week planting of new trees around the Quad will…
Progress – The northern path from Hogg Hall to Skillman Library is being completed. Later this week the remaining concrete base will be poured for the…
Progress – A subcontractor is working on the northern path from Hogg Hall to Skillman Library. Next week the concrete subcontractor will start pouring…
Progress – This week a subcontractor will continue construction of the north path around the Zelkova trees. Clinton Terrace – Later this week, construction…
Progress – The masonry contractor is installing granite at the intersection of High & McCartney and Clinton Terrace. Later this week the Quad’s irrigation…
Progress – The hardscape contractor is installing brick pavers on the newly poured paths between Skillman Library and the Farinon Center. A separate…
To: Lafayette Campus Community From: Offices of Public Safety and Facilities Planning & Construction Re: Update on the Temporary Traffic Adjustments for…
Construction – Crews are pouring concrete slabs for the southern paths between the Farinon Center and Skillman Library, which will allow the hardscape…