Aug 20, 2024
Class of 1962 Gateway Plaza (completed 2023)
The Class of 1962 Gateway Plaza provides a welcoming entrance to campus and is located at the top of the historic steps, between Ruef and Keefe Halls.…
The Class of 1962 Gateway Plaza provides a welcoming entrance to campus and is located at the top of the historic steps, between Ruef and Keefe Halls.…
Construction: The grounds improvement project is wrapping up for the season. The fencing has been removed and the landscape crew is working on the last…
Toll Bridge Rehabilitation Project Repair of the Easton-Phillipsburg (Route 22) Toll Bridge is anticipated to begin in June 2013. The anticipated substantial…
Construction – After the northern path is done early next week, irrigation and landscaping work will continue up to it. Please be cautious of the large…
Construction – New brick pavers and bluestone are being installed along the northern path. Later this week planting of new trees around the Quad will…
Progress – The northern path from Hogg Hall to Skillman Library is being completed. Later this week the remaining concrete base will be poured for the…
Progress – A subcontractor is working on the northern path from Hogg Hall to Skillman Library. Next week the concrete subcontractor will start pouring…
Progress – This week a subcontractor will continue construction of the north path around the Zelkova trees. Clinton Terrace – Later this week, construction…
Progress – The masonry contractor is installing granite at the intersection of High & McCartney and Clinton Terrace. Later this week the Quad’s irrigation…
Progress – The hardscape contractor is installing brick pavers on the newly poured paths between Skillman Library and the Farinon Center. A separate…