Progress – The northern path from Hogg Hall to Skillman Library is being completed. Later this week the remaining concrete base will be poured for the pathways.  Next week pavers will be set and the irrigation system installed.

Gateway Arch (North 3rd Street) – New landscaping will be installed late this week into early next week.

President’s House (McCartney and College Avenue) – A new stone wall is being built to replace the old one.  Pedestrians must use the sidewalk across the street.

Gateway Entrance (High and McCartney) – New walls for the entrance way are being set. The base for the brick paver sidewalk will be installed next week.