Interior renovations and the expansion of the Acopian Engineering Center are completed. Supply chain issues have caused continual delay of the new visual projection systems; however, the spaces are open and available for use, including the fifth floor expansion, to help support Lafayette’s growing engineering program.

Classrooms are open in the 4,000-square-foot Scott Pavilion, made possible by a gift from Walter Scott ’59, including three new classrooms and a glass-collaboration center on the fifth floor. The robotics lab has also been completed on the fifth floor, thanks to a gift from Gary ’01 and Leanne ’02 Anderson and a grant from the McCutchen Foundation.

Renovations to the exterior building entrance, including upgrading the accessible ramp and improving the building’s exterior and visibility, are still underway and on track to be completed in October.