Construction – Crews are pouring concrete slabs for the southern paths between the Farinon Center and Skillman Library, which will allow the hardscape contractor to start setting clay bricks later this week.
A separate crew is setting the asphalt pavers in the new Clinton Terrace turnaround. Once that is done, the masonry contractor will set the remaining granite curb pavers.
Other crews will work on storm water improvements, electrical, and grading.
Major Deliveries – Traffic may be temporarily delayed to allow for the safe unloading of several large deliveries of pavers and granite this week and next week.
Clinton Terrace – Clinton Terrace is only open for deliveries to the Farinon Center.
East Campus Lane – East Campus Lane is open for members of Zeta Psi Fraternity, along with faculty and staff who have assigned spots.
High and Sullivan – When the granite arrives late this week or early next week, High and Sullivan will become one way from east to west. Detour signs will help traffic navigate around campus (see image).