UGI informed Whiting-Turner this morning that it is halfway through the design for the gas line relocation in front of Farinon. UGI is planning on mobilizing it to the site in the middle of next week. This means the gas main will be shut down either late next week or early the following week. Whiting-Turner will update Lafayette as additional information becomes available.
High Street will be one way Tuesday in order to safely mill the road. Drivers should avoid High Street Tuesday.