Progress  This week a subcontractor will continue construction of the north path around the Zelkova trees.

Clinton Terrace – Later this week, construction crews will remove the fencing around the Clinton Terrace circle.  The circle and Pardee’s east entrance will then be open for students, faculty, and staff.

Gateway Arch (North 3rd Street) – The handrail from the bottom of the archway to the first main landing will be painted this week.

President’s House (McCartney and College Ave.) – Crews are constructing a new stone wall. During the day, all pedestrians should use the sidewalk across the street.

Gateway Entrance (High and McCartney) – Demolition is underway to prepare for new brick walls and sidewalks.  Afterward the new footers will be dug and poured for the brick wall.