September 25, 2012

Quad Construction Update Sept. 25, 2012

Progress – The masonry contractor is installing granite at the intersection of High & McCartney and Clinton Terrace. Later this week the Quad’s irrigation system will be brought in. Early next week sod will be placed around the new pathways.

Deliveries – We’re anticipating several large deliveries of granite and sod this week and next. Traffic may be delayed to allow for safe unloading.

Traffic detour

Clinton Terrace – Clinton Terrace is only open for deliveries to the Farinon Center.

East Campus Lane – East Campus Lane is open for members of Zeta Psi Fraternity, along with faculty and staff who have assigned spots.

High and Sullivan – High and Sullivan will remain one way from east to west this week and next. Detour signs help traffic navigate around campus.